Closed
Milestone
Nov 16, 2021–Nov 30, 2021
MS15: Sprint 02 (End Review / Begin Final Integration)
Milestone ID: 90
Planned time line:
- 07.10 - Begin Project (internal) review based off full set of documents
- 13.10 - Internal project meeting to kickoff internal review (1-2h)
- 28.10 - Internal Project Review meeting to end review
- 02.11 – Project meeting
- 05.11 - Begin Public Review / continue internal review
- 29.11 - Project Meeting / Review end / Begin Final integration
- 03.12 - Share Release Candidate with TSC
- 13.12 - TSC