.Required work effort should be less than or equal to committed work effort + service provider contracts
[cols="2,3"]
.Required Effort (man-days)
[%header,cols="2,3*>"]
|===
|WP Category | Project Members |Service Provider |Total
|Language Concepts (WP1-WP8) | 570 |100|670
| Domain Model (WP9-WP13) | 150 |30 |180
| Usage & Pragmatics (WP14-WP18) | 200 |10 |210
| Feature Subsets (WP19) |90 | 10|100
| *Total* |*1010* | *150* | *1160*
|===
.Resource Check
[cols="2,1"]
|===
|*Committed Work Effort* | 1004
|*Committed Work Effort* | 1024
| *Contracted to Service Providers* | 150
| *Required Work Effort* | 1200
| *Required Work Effort* | 1160
|===
==== Budget
This section details the budget required by the project to e.g. pay service providers and the funds to be provided by ASAM. The limits are determined as a factor of the total required work effort.
Project Type Factor
New, major, minor or revision standard development project 0.25
Study project 0.25
Concept project 0.75
[NOTE]
--
This section details the budget required by the project to e.g. pay service providers and the funds to be provided by ASAM. The limits are determined as a factor of the total required work effort. The corresponding effort is allocated a fixed price of 700 EURO per man-day.
.Funding limits
[cols="2,1"]
|===
|Project Type | Factor
|New, major, minor or revision standard development project| 0.25